Order Lifecycle โ Practical Checklist
Once the client approves the project, move through each stage systematically.
Stage 1, Order Confirmation
Verify:
- Product
- Quantity
- Pricing
- Decoration
- Shipping address
- In-hands date
- Client requirements
- Stage 2, Artwork
- Obtain production-ready artwork
- Submit artwork
- Review proof
- Send proof to client
- Obtain approval
- Stage 3, Purchase Order
Confirm:
- Correct supplier
- Correct SKU
- Quantity
- Decoration
- Ship-to address
- Pricing
- Required date
- Artwork/proof requirements
- Stage 4, Production
Monitor:
- Supplier confirmation
- Production start
- Production completion
- Delays or exceptions
- Stage 5, Shipping
Confirm:
- Tracking number
- Carrier
- Ship date
- Expected delivery
- Delivery location
- Stage 6, Delivery
Verify:
- Order delivered
- Quantity received
- Correct product
- No reported damage or shortage
- Stage 7, Closeout
Update:
- CRM/order system
- Tracking information
- Final status
- Notes
- Client follow-up
- Any supplier issue or resolution
In-Hands Date Planning
The in-hands date is one of the most important dates in promotional-products work.
๐ซ Do not work forward from the order date.
Work backward from the required delivery date.
Example
In-Hands Date: June 30
Allow time for:
- Transit
- Production
- Proof approval
- Artwork preparation
- Supplier processing
- Order processing
Backward Planning
June 30 โ In Hands
โ Shipping/Transit
โ Production
โ Proof Approval
โ Artwork
โ Order Processing
โ Product/Supplier Selection
Key Rule
๐ซ Always leave a reasonable buffer when possible.
A product that technically arrives on June 30 may still be risky if there is no contingency for production or shipping delays.
When Something Changes
Promotional-product orders can change after quoting or approval.
Common changes include:
- Product becomes unavailable
- Supplier increases pricing
- Inventory decreases
- Artwork changes
- Client changes quantity
- Client changes shipping address
- Production is delayed
- Client moves the in-hands date
Response Framework
STOP โ VERIFY โ ASSESS โ SOLVE โ COMMUNICATE โ DOCUMENT
๐ซ Do Not:
- Guess
- Promise a date without verification
- Assume inventory is still available
- Ignore a supplier notification
- Proceed with changed artwork without approval